SW-IMS-FRM-013
Post-Implementation Review Template
Version
1.0
Owner
Change Manager
Effective Date
TBD
Review Date
TBD
Post-Implementation Review Template
Purpose
This template is used to review changes after implementation, assess whether objectives were met, identify issues and lessons learned, and capture improvements for future changes. Post-Implementation Reviews (PIRs) support continuous improvement of Swedwise's change management process.
Instructions
- Complete within [TBD - e.g., 7 days] of change implementation
- Involve the change team: Include implementers, technical owners, and affected stakeholders
- Be honest and constructive: Focus on learning, not blame
- Capture lessons learned: Share insights with broader organization
- Define follow-up actions: Address any outstanding issues or improvements
- Update knowledge base: Add learnings to change management knowledge base
Review Information
| Field | Details |
|---|---|
| Change Request ID | [CHG-YYYY-NNN from SW-IMS-FRM-011] |
| Change Title | |
| PIR Date | [YYYY-MM-DD] |
| PIR Facilitator | [Usually Change Manager] |
| Review Participants | [Names of all participants in this review] |
Section 1: Change Summary
Original Change Description:
[Brief summary of what was changed - from original Change Request]
Change Objectives:
[What were the intended outcomes? What was this change supposed to achieve?]
Change Type:
- Standard Change
- Normal Change
- Emergency Change
Original Risk Rating: [ ] Low [ ] Medium [ ] High [ ] Critical
Section 2: Implementation Review
2.1 Implementation Timeline
| Milestone | Planned Date/Time | Actual Date/Time | Variance | Notes |
|---|---|---|---|---|
| Change Approved | ||||
| Implementation Started | ||||
| Implementation Completed | ||||
| Validation Completed | ||||
| Change Closed |
Was implementation completed on schedule?
- Yes - On time
- Yes - Ahead of schedule
- No - Delayed (explain below)
If delayed, what caused the delay?
2.2 Downtime and Service Impact
| Metric | Planned | Actual | Variance |
|---|---|---|---|
| Downtime Duration | [Minutes/hours] | ||
| Services Affected | |||
| Users Impacted |
Was the actual impact within acceptable limits?
- Yes - As expected or better
- No - Greater than expected (explain below)
If impact exceeded expectations, why?
2.3 Resource Utilization
| Resource | Planned | Actual | Variance | Notes |
|---|---|---|---|---|
| Staff Time | [Person-hours] | |||
| Financial Cost | [SEK] | |||
| External Support | ||||
| Other |
Was the change completed within budget?
- Yes - On budget or under
- No - Over budget (explain below)
If over budget, what drove additional costs?
Section 3: Objectives Achievement
3.1 Success Criteria Assessment
Were the change objectives achieved?
| Objective | Success Criterion | Achieved? | Evidence | Notes |
|---|---|---|---|---|
| 1. | [ ] Yes - Fully [ ] Yes - Partially [ ] No |
|||
| 2. | [ ] Yes - Fully [ ] Yes - Partially [ ] No |
|||
| 3. | [ ] Yes - Fully [ ] Yes - Partially [ ] No |
Overall Objectives Achievement:
- Fully Achieved: All objectives met
- Mostly Achieved: Most objectives met; minor gaps
- Partially Achieved: Some objectives met; significant gaps
- Not Achieved: Objectives not met
For any objectives not fully achieved, what is the plan to address?
3.2 Business Benefits Realization
Expected Benefits (from original Change Request):
[List expected benefits]
Benefits Achieved:
| Expected Benefit | Achieved? | Evidence/Measurement | Notes |
|---|---|---|---|
| [ ] Yes - Fully [ ] Yes - Partially [ ] No [ ] Too Early to Tell |
|||
| [ ] Yes - Fully [ ] Yes - Partially [ ] No [ ] Too Early to Tell |
|||
| [ ] Yes - Fully [ ] Yes - Partially [ ] No [ ] Too Early to Tell |
Unexpected Benefits:
[Were there any positive outcomes that weren't anticipated?]
Negative Consequences:
[Were there any negative outcomes that weren't anticipated?]
Section 4: Issues and Incidents
4.1 Implementation Issues
Were there any issues during implementation?
- No issues
- Yes - Minor issues, easily resolved
- Yes - Significant issues, required workarounds
- Yes - Major issues, nearly caused rollback
Issue Log:
| # | Issue Description | Severity | Impact | Resolution | Resolved? |
|---|---|---|---|---|---|
| 1 | [ ] Critical [ ] High [ ] Medium [ ] Low |
[ ] Yes [ ] No | |||
| 2 | [ ] Critical [ ] High [ ] Medium [ ] Low |
[ ] Yes [ ] No | |||
| 3 | [ ] Critical [ ] High [ ] Medium [ ] Low |
[ ] Yes [ ] No |
Root Cause of Issues:
[What fundamentally caused the issues? Planning gaps? Testing gaps? Assumptions?]
4.2 Post-Implementation Incidents
Have there been incidents related to this change since implementation?
- No incidents
- Yes - see details below
Incident Log:
| Incident ID | Description | Date | Severity | Status | Related to Change? |
|---|---|---|---|---|---|
| [ ] Definitely [ ] Possibly [ ] Unclear | |||||
| [ ] Definitely [ ] Possibly [ ] Unclear |
If incidents occurred, what corrective actions are needed?
4.3 Outstanding Issues
Are there unresolved issues from this change?
- No - all issues resolved
- Yes - see outstanding issues below
Outstanding Issues:
| # | Issue | Impact | Owner | Target Resolution Date | Status |
|---|---|---|---|---|---|
| 1 | [ ] In Progress [ ] Planned | ||||
| 2 | [ ] In Progress [ ] Planned |
Section 5: Process Review
5.1 Change Management Process
How well did the change management process work for this change?
| Process Step | Rating | Comments/Improvements |
|---|---|---|
| Change Request Submission | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Impact & Risk Assessment | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Approval Process | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Communication | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Implementation Planning | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Testing & Validation | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Rollback Planning | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Documentation | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Post-Implementation Review | [ ] Excellent [ ] Good [ ] Fair [ ] Poor |
Overall Process Rating: [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Process Strengths:
[What worked well in the change management process?]
Process Weaknesses:
[What didn't work well? Where did the process fall short?]
5.2 Planning and Preparation
Was planning and preparation adequate?
- Yes - Very thorough
- Yes - Adequate
- Somewhat - Some gaps
- No - Significant gaps
Planning Gaps Identified:
[What should have been planned better?]
Preparation Gaps Identified:
[What should have been prepared/ready that wasn't?]
5.3 Testing and Validation
Was testing adequate?
- Yes - Comprehensive testing
- Yes - Adequate testing
- Somewhat - Some testing gaps
- No - Insufficient testing
Testing Gaps:
[What should have been tested that wasn't? What tests were inadequate?]
Validation Process:
- Effective - Quickly confirmed success
- Adequate - Validation worked but could be improved
- Inadequate - Validation process had gaps
Validation Improvements:
5.4 Communication
Was communication effective?
| Stakeholder Group | Communication Rating | Comments |
|---|---|---|
| Change Team | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Affected Users | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Management | [ ] Excellent [ ] Good [ ] Fair [ ] Poor | |
| Customers | [ ] Excellent [ ] Good [ ] Fair [ ] Poor [ ] N/A |
Communication Strengths:
Communication Gaps:
Section 6: Risk Management
6.1 Risk Assessment Accuracy
Were the identified risks accurate?
- Yes - Identified risks materialized as expected
- Mostly - Most risks were accurate
- Partially - Some risks missed, some didn't materialize
- No - Risk assessment was inaccurate
Risks That Materialized:
| Risk (from Impact Assessment) | Did It Occur? | Was Mitigation Effective? | Notes |
|---|---|---|---|
| [ ] Yes [ ] No | [ ] Yes [ ] No [ ] N/A | ||
| [ ] Yes [ ] No | [ ] Yes [ ] No [ ] N/A |
Risks That Were Missed:
[What risks should have been identified but weren't?]
Risks That Didn't Materialize:
[What risks were identified but didn't occur? Were they over-estimated?]
6.2 Risk Mitigation Effectiveness
Were risk mitigation measures effective?
- Yes - Very effective
- Yes - Mostly effective
- Partially - Some mitigations worked, others didn't
- No - Mitigations were ineffective
Effective Mitigations:
[What mitigations worked well and should be reused?]
Ineffective Mitigations:
[What mitigations didn't work and should be reconsidered?]
Section 7: Lessons Learned
7.1 What Went Well
What aspects of this change should be repeated in future changes?
Best Practices Identified:
[Practices that worked exceptionally well and should become standard]
7.2 What Didn't Go Well
What aspects of this change should be avoided or improved in future changes?
Anti-Patterns Identified:
[Approaches that clearly didn't work and should be avoided]
7.3 What We Learned
Key insights and learnings from this change:
Knowledge Gaps Identified:
[What did we realize we didn't know? Where do we need more expertise?]
Skill Gaps Identified:
[What skills do we need to develop for future changes?]
7.4 Recommendations
Specific recommendations for future changes:
Process Improvements:
Technical Improvements:
Competence/Training Needs:
Section 8: Follow-Up Actions
8.1 Immediate Actions
Actions required immediately to address outstanding issues or risks:
| # | Action | Owner | Due Date | Status |
|---|---|---|---|---|
| 1 | [ ] Not Started [ ] In Progress [ ] Complete | |||
| 2 | [ ] Not Started [ ] In Progress [ ] Complete | |||
| 3 | [ ] Not Started [ ] In Progress [ ] Complete |
8.2 Process Improvement Actions
Actions to improve the change management process based on this review:
| # | Improvement Action | Owner | Target Date | Link to Process |
|---|---|---|---|---|
| 1 | [Which procedure/form to update?] | |||
| 2 | ||||
| 3 |
Submit improvement suggestions using SW-IMS-FRM-002 (Improvement Suggestion Form).
8.3 Knowledge Sharing
How will lessons from this change be shared?
- Update change management knowledge base
- Add to standard change procedures (if applicable)
- Present at team meeting
- Include in change management training
- Document in procedure/guideline
- Share in CAB meeting
- Other: _______________________
Knowledge Base Updated? [ ] Yes [ ] No [ ] N/A
Shared With: [Teams, individuals, or forums]
Section 9: Overall Assessment
9.1 Change Success Rating
Overall, how successful was this change?
- Highly Successful: Exceeded expectations; smooth implementation; all objectives achieved
- Successful: Met expectations; minor issues; objectives achieved
- Moderately Successful: Some challenges; most objectives achieved; lessons learned
- Unsuccessful: Significant issues; objectives not met; required remediation
- Failed: Change rolled back or caused serious problems
Rationale for Rating:
9.2 Would We Do This Change Again?
Given what we know now, would we still do this change?
- Yes - Definitely worth it
- Yes - Benefits outweigh costs/issues
- Maybe - Marginal benefits
- No - Not worth the effort/risk
- No - Should have chosen different approach
Explanation:
If we had to do a similar change again, what would we do differently?
Section 10: PIR Completion
10.1 Review Summary
PIR Completed By: _______________________
PIR Completion Date: [YYYY-MM-DD]
PIR Status: [ ] Complete [ ] Pending Follow-Up Actions
Key Takeaways (3-5 bullet points):
10.2 Approval
PIR Reviewed and Approved By:
| Name | Role | Date | Signature |
|---|---|---|---|
| Change Manager | |||
| Technical Owner | |||
| Service Owner (if different) |
10.3 Distribution
This PIR has been shared with:
- Change Management team
- Change Advisory Board (CAB)
- Management Team
- Technical Teams
- Change Requester
- Affected Stakeholders
- Other: _______________________
Notes for Users
When to Conduct a PIR
Mandatory PIR for:
- High/Critical risk changes
- Emergency changes
- Changes that were rolled back
- Changes with significant implementation issues
- Changes that exceeded budget or timeline by >20%
- Changes requested by management or CAB
- Changes affecting SaaS platform or customer-facing services
Optional PIR for:
- Low-risk standard changes that went smoothly
- Routine changes with no issues
Timing:
- Initial PIR: Within 7 days of implementation
- Follow-Up PIR (if needed): 30-90 days post-implementation for benefit realization assessment
PIR vs. Blame
PIRs are NOT about blame. They are about:
- Learning: What can we learn from this experience?
- Improving: How can we do better next time?
- Sharing: How can we help others avoid similar issues?
PIRs should foster:
- Psychological safety: People feel safe admitting mistakes
- Constructive discussion: Focus on systems and processes, not individuals
- Action-oriented thinking: What will we do differently?
If someone made an error, focus on:
- Why was the error possible? (system/process gap)
- How can we prevent similar errors? (controls, training, procedures)
- NOT: Who is to blame?
Conducting Effective PIRs
Preparation:
- Review all change documentation (CR, impact assessment, implementation logs)
- Gather metrics (actual vs. planned time, cost, downtime)
- Collect stakeholder feedback
- Identify discussion topics in advance
Facilitation:
- Keep discussion focused and time-boxed
- Encourage all participants to contribute
- Capture insights in real-time (don't rely on memory later)
- Use "5 Whys" or similar techniques for root cause analysis
- Balance critique with recognition of what went well
Follow-Through:
- Document lessons learned while fresh
- Assign follow-up actions with clear ownership
- Share insights with broader organization
- Actually implement process improvements (PIRs are wasted if learnings aren't applied)
Common PIR Findings
Typical "What Went Well":
- Thorough testing caught issues before production
- Clear communication prevented confusion
- Good rollback plan provided confidence
- Cross-functional collaboration was effective
Typical "What Didn't Go Well":
- Inadequate testing (especially integration/performance testing)
- Poor communication to affected users
- Unexpected dependencies or interactions
- Insufficient rollback testing
- Overly optimistic timelines
- Inadequate understanding of current state before change
Typical Lessons Learned:
- Involve stakeholders earlier in planning
- Test in production-like environments
- Verify assumptions before implementation
- Communicate more than you think necessary
- Plan for worst case, not best case
- Don't skip rollback testing
Integrating PIR Insights
PIR lessons should feed into:
- Change Management Process: Update procedures, templates, checklists
- Training: Update training materials with real examples
- Knowledge Base: Build library of change patterns, solutions, and pitfalls
- Risk Assessment: Improve risk identification and estimation
- Standard Changes: Document successful patterns as pre-approved standard changes
- Continuous Improvement: Submit improvements via SW-IMS-FRM-002
PIR Documentation and Retention
- Store: In change management system alongside change record
- Retain: Minimum [TBD - e.g., 3 years] or as required by ISO audit
- Access: Available to all change management participants and CAB
- Summary Reports: Periodic summaries (quarterly/annually) of PIR trends and aggregate learnings
Document Control
| Version | Date | Author | Changes | Approved By |
|---|---|---|---|---|
| 1.0 | [TBD] | Change Manager | Initial template creation | [TBD] |
Next Review Date: [TBD]
Document Classification: Internal
Document Owner: Change Manager