DraftInternalISO 9001ISO 27001

SW-IMS-FRM-013

Post-Implementation Review Template

Version

1.0

Owner

Change Manager

Effective Date

TBD

Review Date

TBD

Post-Implementation Review Template

Purpose

This template is used to review changes after implementation, assess whether objectives were met, identify issues and lessons learned, and capture improvements for future changes. Post-Implementation Reviews (PIRs) support continuous improvement of Swedwise's change management process.

Instructions

  1. Complete within [TBD - e.g., 7 days] of change implementation
  2. Involve the change team: Include implementers, technical owners, and affected stakeholders
  3. Be honest and constructive: Focus on learning, not blame
  4. Capture lessons learned: Share insights with broader organization
  5. Define follow-up actions: Address any outstanding issues or improvements
  6. Update knowledge base: Add learnings to change management knowledge base

Review Information

Field Details
Change Request ID [CHG-YYYY-NNN from SW-IMS-FRM-011]
Change Title
PIR Date [YYYY-MM-DD]
PIR Facilitator [Usually Change Manager]
Review Participants [Names of all participants in this review]

Section 1: Change Summary

Original Change Description:

[Brief summary of what was changed - from original Change Request]

Change Objectives:

[What were the intended outcomes? What was this change supposed to achieve?]

Change Type:

  • Standard Change
  • Normal Change
  • Emergency Change

Original Risk Rating: [ ] Low [ ] Medium [ ] High [ ] Critical


Section 2: Implementation Review

2.1 Implementation Timeline

Milestone Planned Date/Time Actual Date/Time Variance Notes
Change Approved
Implementation Started
Implementation Completed
Validation Completed
Change Closed

Was implementation completed on schedule?

  • Yes - On time
  • Yes - Ahead of schedule
  • No - Delayed (explain below)

If delayed, what caused the delay?

2.2 Downtime and Service Impact

Metric Planned Actual Variance
Downtime Duration [Minutes/hours]
Services Affected
Users Impacted

Was the actual impact within acceptable limits?

  • Yes - As expected or better
  • No - Greater than expected (explain below)

If impact exceeded expectations, why?

2.3 Resource Utilization

Resource Planned Actual Variance Notes
Staff Time [Person-hours]
Financial Cost [SEK]
External Support
Other

Was the change completed within budget?

  • Yes - On budget or under
  • No - Over budget (explain below)

If over budget, what drove additional costs?


Section 3: Objectives Achievement

3.1 Success Criteria Assessment

Were the change objectives achieved?

Objective Success Criterion Achieved? Evidence Notes
1. [ ] Yes - Fully
[ ] Yes - Partially
[ ] No
2. [ ] Yes - Fully
[ ] Yes - Partially
[ ] No
3. [ ] Yes - Fully
[ ] Yes - Partially
[ ] No

Overall Objectives Achievement:

  • Fully Achieved: All objectives met
  • Mostly Achieved: Most objectives met; minor gaps
  • Partially Achieved: Some objectives met; significant gaps
  • Not Achieved: Objectives not met

For any objectives not fully achieved, what is the plan to address?

3.2 Business Benefits Realization

Expected Benefits (from original Change Request):

[List expected benefits]

Benefits Achieved:

Expected Benefit Achieved? Evidence/Measurement Notes
[ ] Yes - Fully
[ ] Yes - Partially
[ ] No
[ ] Too Early to Tell
[ ] Yes - Fully
[ ] Yes - Partially
[ ] No
[ ] Too Early to Tell
[ ] Yes - Fully
[ ] Yes - Partially
[ ] No
[ ] Too Early to Tell

Unexpected Benefits:

[Were there any positive outcomes that weren't anticipated?]

Negative Consequences:

[Were there any negative outcomes that weren't anticipated?]


Section 4: Issues and Incidents

4.1 Implementation Issues

Were there any issues during implementation?

  • No issues
  • Yes - Minor issues, easily resolved
  • Yes - Significant issues, required workarounds
  • Yes - Major issues, nearly caused rollback

Issue Log:

# Issue Description Severity Impact Resolution Resolved?
1 [ ] Critical
[ ] High
[ ] Medium
[ ] Low
[ ] Yes [ ] No
2 [ ] Critical
[ ] High
[ ] Medium
[ ] Low
[ ] Yes [ ] No
3 [ ] Critical
[ ] High
[ ] Medium
[ ] Low
[ ] Yes [ ] No

Root Cause of Issues:

[What fundamentally caused the issues? Planning gaps? Testing gaps? Assumptions?]

4.2 Post-Implementation Incidents

Have there been incidents related to this change since implementation?

  • No incidents
  • Yes - see details below

Incident Log:

Incident ID Description Date Severity Status Related to Change?
[ ] Definitely [ ] Possibly [ ] Unclear
[ ] Definitely [ ] Possibly [ ] Unclear

If incidents occurred, what corrective actions are needed?

4.3 Outstanding Issues

Are there unresolved issues from this change?

  • No - all issues resolved
  • Yes - see outstanding issues below

Outstanding Issues:

# Issue Impact Owner Target Resolution Date Status
1 [ ] In Progress [ ] Planned
2 [ ] In Progress [ ] Planned

Section 5: Process Review

5.1 Change Management Process

How well did the change management process work for this change?

Process Step Rating Comments/Improvements
Change Request Submission [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Impact & Risk Assessment [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Approval Process [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Communication [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Implementation Planning [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Testing & Validation [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Rollback Planning [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Documentation [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Post-Implementation Review [ ] Excellent [ ] Good [ ] Fair [ ] Poor

Overall Process Rating: [ ] Excellent [ ] Good [ ] Fair [ ] Poor

Process Strengths:

[What worked well in the change management process?]

Process Weaknesses:

[What didn't work well? Where did the process fall short?]

5.2 Planning and Preparation

Was planning and preparation adequate?

  • Yes - Very thorough
  • Yes - Adequate
  • Somewhat - Some gaps
  • No - Significant gaps

Planning Gaps Identified:

[What should have been planned better?]

Preparation Gaps Identified:

[What should have been prepared/ready that wasn't?]

5.3 Testing and Validation

Was testing adequate?

  • Yes - Comprehensive testing
  • Yes - Adequate testing
  • Somewhat - Some testing gaps
  • No - Insufficient testing

Testing Gaps:

[What should have been tested that wasn't? What tests were inadequate?]

Validation Process:

  • Effective - Quickly confirmed success
  • Adequate - Validation worked but could be improved
  • Inadequate - Validation process had gaps

Validation Improvements:

5.4 Communication

Was communication effective?

Stakeholder Group Communication Rating Comments
Change Team [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Affected Users [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Management [ ] Excellent [ ] Good [ ] Fair [ ] Poor
Customers [ ] Excellent [ ] Good [ ] Fair [ ] Poor [ ] N/A

Communication Strengths:

Communication Gaps:


Section 6: Risk Management

6.1 Risk Assessment Accuracy

Were the identified risks accurate?

  • Yes - Identified risks materialized as expected
  • Mostly - Most risks were accurate
  • Partially - Some risks missed, some didn't materialize
  • No - Risk assessment was inaccurate

Risks That Materialized:

Risk (from Impact Assessment) Did It Occur? Was Mitigation Effective? Notes
[ ] Yes [ ] No [ ] Yes [ ] No [ ] N/A
[ ] Yes [ ] No [ ] Yes [ ] No [ ] N/A

Risks That Were Missed:

[What risks should have been identified but weren't?]

Risks That Didn't Materialize:

[What risks were identified but didn't occur? Were they over-estimated?]

6.2 Risk Mitigation Effectiveness

Were risk mitigation measures effective?

  • Yes - Very effective
  • Yes - Mostly effective
  • Partially - Some mitigations worked, others didn't
  • No - Mitigations were ineffective

Effective Mitigations:

[What mitigations worked well and should be reused?]

Ineffective Mitigations:

[What mitigations didn't work and should be reconsidered?]


Section 7: Lessons Learned

7.1 What Went Well

What aspects of this change should be repeated in future changes?

Best Practices Identified:

[Practices that worked exceptionally well and should become standard]

7.2 What Didn't Go Well

What aspects of this change should be avoided or improved in future changes?

Anti-Patterns Identified:

[Approaches that clearly didn't work and should be avoided]

7.3 What We Learned

Key insights and learnings from this change:

Knowledge Gaps Identified:

[What did we realize we didn't know? Where do we need more expertise?]

Skill Gaps Identified:

[What skills do we need to develop for future changes?]

7.4 Recommendations

Specific recommendations for future changes:

Process Improvements:

Technical Improvements:

Competence/Training Needs:


Section 8: Follow-Up Actions

8.1 Immediate Actions

Actions required immediately to address outstanding issues or risks:

# Action Owner Due Date Status
1 [ ] Not Started [ ] In Progress [ ] Complete
2 [ ] Not Started [ ] In Progress [ ] Complete
3 [ ] Not Started [ ] In Progress [ ] Complete

8.2 Process Improvement Actions

Actions to improve the change management process based on this review:

# Improvement Action Owner Target Date Link to Process
1 [Which procedure/form to update?]
2
3

Submit improvement suggestions using SW-IMS-FRM-002 (Improvement Suggestion Form).

8.3 Knowledge Sharing

How will lessons from this change be shared?

  • Update change management knowledge base
  • Add to standard change procedures (if applicable)
  • Present at team meeting
  • Include in change management training
  • Document in procedure/guideline
  • Share in CAB meeting
  • Other: _______________________

Knowledge Base Updated? [ ] Yes [ ] No [ ] N/A

Shared With: [Teams, individuals, or forums]


Section 9: Overall Assessment

9.1 Change Success Rating

Overall, how successful was this change?

  • Highly Successful: Exceeded expectations; smooth implementation; all objectives achieved
  • Successful: Met expectations; minor issues; objectives achieved
  • Moderately Successful: Some challenges; most objectives achieved; lessons learned
  • Unsuccessful: Significant issues; objectives not met; required remediation
  • Failed: Change rolled back or caused serious problems

Rationale for Rating:

9.2 Would We Do This Change Again?

Given what we know now, would we still do this change?

  • Yes - Definitely worth it
  • Yes - Benefits outweigh costs/issues
  • Maybe - Marginal benefits
  • No - Not worth the effort/risk
  • No - Should have chosen different approach

Explanation:

If we had to do a similar change again, what would we do differently?


Section 10: PIR Completion

10.1 Review Summary

PIR Completed By: _______________________

PIR Completion Date: [YYYY-MM-DD]

PIR Status: [ ] Complete [ ] Pending Follow-Up Actions

Key Takeaways (3-5 bullet points):

10.2 Approval

PIR Reviewed and Approved By:

Name Role Date Signature
Change Manager
Technical Owner
Service Owner (if different)

10.3 Distribution

This PIR has been shared with:

  • Change Management team
  • Change Advisory Board (CAB)
  • Management Team
  • Technical Teams
  • Change Requester
  • Affected Stakeholders
  • Other: _______________________

Notes for Users

When to Conduct a PIR

Mandatory PIR for:

  • High/Critical risk changes
  • Emergency changes
  • Changes that were rolled back
  • Changes with significant implementation issues
  • Changes that exceeded budget or timeline by >20%
  • Changes requested by management or CAB
  • Changes affecting SaaS platform or customer-facing services

Optional PIR for:

  • Low-risk standard changes that went smoothly
  • Routine changes with no issues

Timing:

  • Initial PIR: Within 7 days of implementation
  • Follow-Up PIR (if needed): 30-90 days post-implementation for benefit realization assessment

PIR vs. Blame

PIRs are NOT about blame. They are about:

  • Learning: What can we learn from this experience?
  • Improving: How can we do better next time?
  • Sharing: How can we help others avoid similar issues?

PIRs should foster:

  • Psychological safety: People feel safe admitting mistakes
  • Constructive discussion: Focus on systems and processes, not individuals
  • Action-oriented thinking: What will we do differently?

If someone made an error, focus on:

  • Why was the error possible? (system/process gap)
  • How can we prevent similar errors? (controls, training, procedures)
  • NOT: Who is to blame?

Conducting Effective PIRs

Preparation:

  • Review all change documentation (CR, impact assessment, implementation logs)
  • Gather metrics (actual vs. planned time, cost, downtime)
  • Collect stakeholder feedback
  • Identify discussion topics in advance

Facilitation:

  • Keep discussion focused and time-boxed
  • Encourage all participants to contribute
  • Capture insights in real-time (don't rely on memory later)
  • Use "5 Whys" or similar techniques for root cause analysis
  • Balance critique with recognition of what went well

Follow-Through:

  • Document lessons learned while fresh
  • Assign follow-up actions with clear ownership
  • Share insights with broader organization
  • Actually implement process improvements (PIRs are wasted if learnings aren't applied)

Common PIR Findings

Typical "What Went Well":

  • Thorough testing caught issues before production
  • Clear communication prevented confusion
  • Good rollback plan provided confidence
  • Cross-functional collaboration was effective

Typical "What Didn't Go Well":

  • Inadequate testing (especially integration/performance testing)
  • Poor communication to affected users
  • Unexpected dependencies or interactions
  • Insufficient rollback testing
  • Overly optimistic timelines
  • Inadequate understanding of current state before change

Typical Lessons Learned:

  • Involve stakeholders earlier in planning
  • Test in production-like environments
  • Verify assumptions before implementation
  • Communicate more than you think necessary
  • Plan for worst case, not best case
  • Don't skip rollback testing

Integrating PIR Insights

PIR lessons should feed into:

  • Change Management Process: Update procedures, templates, checklists
  • Training: Update training materials with real examples
  • Knowledge Base: Build library of change patterns, solutions, and pitfalls
  • Risk Assessment: Improve risk identification and estimation
  • Standard Changes: Document successful patterns as pre-approved standard changes
  • Continuous Improvement: Submit improvements via SW-IMS-FRM-002

PIR Documentation and Retention

  • Store: In change management system alongside change record
  • Retain: Minimum [TBD - e.g., 3 years] or as required by ISO audit
  • Access: Available to all change management participants and CAB
  • Summary Reports: Periodic summaries (quarterly/annually) of PIR trends and aggregate learnings

Document Control

Version Date Author Changes Approved By
1.0 [TBD] Change Manager Initial template creation [TBD]

Next Review Date: [TBD]

Document Classification: Internal

Document Owner: Change Manager